Electricity and Lighting has been turned on. Bathroom tile also done.















Only a few more weeks left until the house will be done. Stay Tuned.

Saturday, November 19, 2011

Brick work complete, stair railing installed and trim work in progress!

 Finally Finished with the Brick.
 Stair Railing is up.


 Basement stair railing is up.

 Wet bar



 Our address is on the new house.
 Three Car side garage

 Garage side view.

Thursday, November 17, 2011

Cabinets and Trim Installed! Brick almost done!


 Kitchen Cabinets Looking Great!

 Mother's Office.

 Basement Bath


 Basement Wetbar

 Master Bath His
 Master Bath Hers
 Master Bath Entrance

Tuesday, November 15, 2011

Brick and Stone is finally being placed! First coat of paint! Cabinets delivered today!


 Front porch stone and brick almost complete!
 Side of house brick completed!
 Cabinets delivered


Vanity Tops Delivered.

First coat of paint added today!

Tuesday, November 8, 2011

Drywall is Hung and ready for mud and sanding!

Front Door Foyer
Family room looking into kitchen.
Family Room
Front door and dining room.
Master BR/ tray ceiling.
Entrance to Theater Room.
Wet-bar and lounge area.
Workout room, bathroom, and hvac area.

Much more to come, stay tuned.....

Thursday, November 3, 2011